Do I Need a Permit for a Pole Barn on a Farm in Kentucky?
Guide

Do I Need a Permit for a Pole Barn on a Farm in Kentucky?

Kentucky has a farmstead exemption that can take a qualifying farm building, like a pole barn used for the farm, out of the state building code's permit and inspection rules. Whether your barn qualifies, and what local rules still apply, is a question for your county office before you build.

Want this done for you?

Once the county has answered, Trey builds the pad: site stripped, cut and filled level, packed in lifts and stoned, with a gravel approach, from Campbellsville and Lebanon out across central Kentucky. More on our pole barn pads page. Call (270) 272-8739 or send the form for a straight quote.

The short answer: call your county first

Do not assume your barn needs no permit, and do not assume it needs a full one. Kentucky's building rules come from the state, and many counties and cities enforce them through their own planning, zoning or building office. The state also has a farmstead exemption for qualifying farm buildings. Which rules apply to your barn depends on your land, what the barn is for and where it sits. So before the kit is ordered, call the county or city office that covers your address. Tell them the size, the use and the acreage, and ask what they need.

The farmstead exemption

The Kentucky Department of Housing, Buildings and Construction publishes an Affidavit for Farmstead Exemption. County versions of that form, such as the one Boyle County uses, cite KRS 198B.060 and the state building code regulations. On the Boyle form, the owner swears to several things. The land is registered as a farm with the county PVA. The building sits on a lot of at least 10 acres, outside city limits. It is a dwelling, or a building incidental to the farm, such as a barn or a shed. It is not a commercial or public building where 10 or more people regularly work, and it is not used to process or store timber products.

What can still apply

An exemption from the building code is not an exemption from everything. The Boyle form asks whether the building is in a floodplain and whether floodplain permits have been issued, and the owner acknowledges that no construction inspections will be made. Electrical work, plumbing, septic and zoning setbacks can each have their own rules, and some counties ask for a site plan. Counties handle this differently, and some have their own fee or form. Get the answer from your own county office in writing if you can.

A shop that is not for the farm

The exemption is for farm buildings. A metal shop on a house lot, a building for a business, or a barn on a few acres that are not classified as a farm may be handled differently. A building where people regularly work, or one used for processing or storing timber products, is called out on the forms. If you are not sure which side of the line your building falls on, ask the county before you sign anything. It is much easier to sort out on paper than after the posts are set.

Floodplain, setbacks and the spot you pick

Even a building that qualifies has to sit somewhere sensible. Low ground near a creek or river may be in a mapped floodplain, and that can bring its own state and local permits. Zoning may set how close a building can be to a road or a property line. These questions often decide where the barn goes, so settle them before the pad is staked. Trey will ask where the lines are and how the site drains, and he will steer the pad toward firm ground above the wet.

Before we dig the pad

Kentucky 811 has to be notified at least two and no more than ten full working days before any machine digging, and the ticket is good for 21 calendar days. That covers the cut for a barn pad. The locators mark public lines only, so the water line to a trough or the power to an old barn is yours to point out. Have the county answer in hand, the barn's size from your supplier, and the corners staked. Then the pad can go in without surprises. See our shop and pole barn pads page and the pole barn pad cost guide.

What to do next

Ask your county office first, since the rules belong to them. Then call (270) 272-8739 or send the form, and Trey will look at the spot, talk through the pad your barn needs and give you a straight quote before work starts.

Ready when you are

With the county answer and your barn size in hand, Trey will look at the spot and give you a straight quote.

See our shop & pole barn pads service, call (270) 272-8739 or contact us.

Building Pads near you

Every Job Is Different

Want a Number for Your Job?

Guides can only tell you what drives the cost. Trey looks at the site, talks through what you want and gives you a straight quote before any work starts.

  • Only your name and phone are required
  • Residential, farm and commercial jobs
  • Rather talk now? Call (270) 272-8739

Tell us about the job

Only your name and phone are required.

Call NowGet a Quote